Monday, August 29, 2016

House Renovation Week 11: Windows!

This week saw the installation of most of the windows. We finally got to see what the front of our house is truly going to look like when finished. Also this week the footings for the mud room and front stairs.


MONDAY


On Monday, the footings were dug for the front hall and the new stairs to the basement were installed.

TUESDAY



The new dining room windows were installed on Tuesday. These three windows are one solid piece, our contractor said it was quite heavy. These windows replace the fireplace and mantle.


WEDNESDAY




All the windows in the front of the house were installed and a couple on the side. This house is coming together.


The footings for the front hall and front stairs were started.

THURSDAY







All the windows except for the large fixed window were installed on Thursday. Rain should no longer be an issue for us.


FRIDAY






By the end of the week we had windows! The footings for the front hall, stairs and deck stairs were poured. We also ordered our bathroom faucets and shower controls. It is going to be a very busy fall with all the decisions we have to make in the next few months.