MONDAY
On Monday, the footings were dug for the front hall and the new stairs to the basement were installed.
TUESDAY
The new dining room windows were installed on Tuesday. These three windows are one solid piece, our contractor said it was quite heavy. These windows replace the fireplace and mantle.
WEDNESDAY
All the windows in the front of the house were installed and a couple on the side. This house is coming together.
The footings for the front hall and front stairs were started.
THURSDAY
All the windows except for the large fixed window were installed on Thursday. Rain should no longer be an issue for us.
FRIDAY
By the end of the week we had windows! The footings for the front hall, stairs and deck stairs were poured. We also ordered our bathroom faucets and shower controls. It is going to be a very busy fall with all the decisions we have to make in the next few months.